Commercial Net Metering Guide

Commercial Solar Net Metering In Delhi NCR: BSES vs DHBVN vs PVVNL Rules Compared

Brightleaf Energy Commercial Solar Team
October 20, 2026
10 Min Read
Bi-directional solar meter installed at a commercial property in Delhi NCR — net metering for business rooftop solar
Net metering capacity, meters and credit rules differ by utility — Haryana caps net-metered plants at 500 kW.

Net metering lets a commercial consumer export surplus rooftop solar into the grid and receive it back as bill credit through a bi-directional meter. Across Delhi NCR it is available under all three utility families — Delhi (BSES Rajdhani, BSES Yamuna and Tata Power-DDL), Haryana (DHBVN) and Uttar Pradesh (PVVNL, plus NPCL in Greater Noida) — generally up to 100% of your sanctioned load, with Haryana applying a 500 kW regulatory cap on net-metered installations.

Rules differ enough between utilities that a project designed for one can stall in another. This guide compares them side by side and links to city-level detail: commercial solar for Delhi businesses, PVVNL net metering support in Noida, commercial solar in Greater Noida under NPCL, commercial solar in Ghaziabad, commercial solar in Faridabad and DHBVN net metering up to 500 kW in Gurugram.

Last updated: October 2026. Regulatory frameworks and utility processes change. Treat everything below as a working summary to plan against, and confirm current caps, forms and charges with your DISCOM division or your chartered accountant at the feasibility stage.

home solar installation step-by-step guide, solar installation process in India, solar payback period and cost recovery time and solar blogs and guides.

Reviewed by DISCOM Liaison Lead

The single biggest cause of delay is incomplete documentation, not engineering. A mismatch between the name on the electricity bill and the entity applying for the meter, a missing lease or ownership document, or an unsigned single-line drawing can add weeks to a project that is otherwise ready to build.

What Net Metering Actually Does

A grid-connected commercial solar system has two energy flows. Units your building consumes during the day are consumed directly on site. Anything more — during a weekend, a holiday, or a light-load period — flows out through the meter and is recorded as export. Under net metering, that exported energy is credited back against your consumption in subsequent billing periods, so surplus generation is banked rather than wasted.

Without a net metering arrangement, an oversized array earns nothing beyond its own self-consumption. That is why the DISCOM framework, not the module price, determines whether a large commercial system is financially sensible.

Import and export

A bi-directional meter records both flows separately, so the utility can bill import and credit export in the same billing cycle.

Capacity, not roof size

Sanctioned load and feeder capacity decide how much you may install — not the square footage of the roof.

The Comparison At A Glance

ParameterDelhi (BSES Rajdhani, BSES Yamuna, Tata Power-DDL)Haryana (DHBVN)Uttar Pradesh (PVVNL — Noida, Ghaziabad)Greater Noida (NPCL)
Governing frameworkDERC green energy / net metering regulations for the licensed DISCOMsHaryana rooftop solar regulations under HERC; Haryana Solar PolicyUttar Pradesh Solar Power PolicyUP Solar Policy, administered by NPCL
Eligible consumerCommercial, industrial and institutional connectionsCommercial, industrial and institutional connectionsCommercial, industrial and institutional connectionsCommercial, industrial and institutional connections
Capacity basisSanctioned load / contract demand, subject to current regulationsUp to 100% of sanctioned connected load / contract demandUp to 100% of sanctioned connected loadUp to sanctioned load, per NPCL process
Net-metered capacity capConfirm current limit with the DISCOM division during feasibilityRegulatory cap of 500 kW for net-metered installationsPolicy-based limits apply; larger consumers shift toward gross meteringPolicy-based limits apply
MeteringBi-directional meterFour-quadrant bi-directional TOD meterBi-directional meterBi-directional meter
Credit mechanismExport recorded and adjusted in the billing cycleMonthly kWh credits that roll forward through the financial yearExported units adjusted against the monthly bill, rolled forward to annual settlementExported units credited at approved UPERC tariff benchmarks
HT interconnectionPer utility requirement for larger plantsPlants above 50 kW typically at 11 kV / 33 kV with dual-protection relaysPlants above 50 kW at 11 kV / 33 kV with dual-protection relaysPer NPCL requirement for larger plants
CEIG involvementElectrical safety clearance per current rulesDrawing approval and inspection for plants above 100 kW or on 11/33 kV HTElectrical safety approvals via CEIG for applicable capacitiesElectrical safety approvals via CEIG for applicable capacities
Application routeUtility portal / division officeDHBVN Solar Portal (sfa.dhbvn.org.in)PVVNL division office / portalNPCL division office / portal
City supportDelhi beltGurugram, FaridabadNoida, GhaziabadGreater Noida

Summary only. Capacity caps, credit settlement and documentation requirements should be confirmed with the specific division before layout is frozen.

Delhi: BSES Rajdhani, BSES Yamuna And Tata Power-DDL

Delhi’s commercial net metering is administered by the three licensed distribution companies under the DERC green energy framework, which sets the eligibility, metering and settlement rules alongside the rooftop solar incentive framework for the city.

In practice for a business:

  • The bi-directional net meter is the deliverable that unlocks export credits, and it is installed after technical feasibility approval.
  • Commercial payback in Delhi typically runs 3–6 years, driven by tariff level, self-consumption ratio and whether the 40% Year-1 depreciation under Section 32 is usable against your profits.
  • Both CAPEX and RESCO models work in Delhi; a RESCO structure is common where the building is leased.
  • Export limits and capacity caps are regulatory, not negotiable — they should be confirmed with your specific division before the array layout is frozen, because they determine your system size.

Brightleaf’s Delhi team handles documentation, feasibility applications and DISCOM coordination end to end, so your project does not stall in an approval queue. See the Delhi commercial solar page for the local process.

Haryana: DHBVN And The 500 kW Cap

Haryana’s framework is the most explicit of the three, which makes Gurugram and Faridabad projects straightforward to plan.

  • Capacity: commercial rooftop solar up to 100% of sanctioned connected load or contract demand, with a regulatory cap of 500 kW for net-metered installations.
  • Meter: four-quadrant bi-directional TOD (Time of Day) meter.
  • Settlement: exported units are credited on the monthly bill, with kWh credits rolling forward through the financial year — so a weekend’s surplus offsets a weekday’s peak.
  • Application: filed online through the DHBVN Solar Portal (sfa.dhbvn.org.in), followed by processing fee payment and technical feasibility approval.
  • CEIG: electrical drawing approval and inspection from the Chief Electrical Inspector to the Government of Haryana are required for plants above 100 kW or on 11 kV / 33 kV HT supplies.
Typical DHBVN sequence

Site survey and structural audit (days 1–3) → PV engineering and SLD (days 4–7) → portal filing and feasibility (days 8–18) → CEIG drawing approval (days 19–28) → installation and earthing (days 25–45) → CEIG inspection and net-meter commissioning (days 45–55) → energisation and SCADA handover (~day 60).

For a detailed view of how this plays out on a Gurugram industrial rooftop, see DHBVN net metering up to 500 kW in Gurugram, and the Faridabad equivalent on our commercial solar in Faridabad page.

Uttar Pradesh: PVVNL And NPCL

Noida, Ghaziabad and Greater Noida sit under UP policy but different licensees.

PVVNL (Noida, Ghaziabad)

  • Commercial and industrial consumers can install grid-connected rooftop solar up to 100% of sanctioned connected load.
  • Net metering and gross metering both operate under the UP Solar Power Policy — the arrangement that fits your capacity and load profile determines which applies.
  • A bi-directional meter records import and export; exported units are adjusted against your monthly bill, with credits carried forward across billing cycles to the annual settlement.
  • Plants above 50 kW are typically connected at 11 kV or 33 kV with dual-protection relays, so the electrical scope includes switchgear and protection coordination.
  • CEIG electrical safety approvals apply for relevant capacities, alongside PVVNL paperwork, transformer capacity verification and meter testing.

NPCL (Greater Noida)

  • Net metering for businesses under NPCL, with surplus generation credited against the bill cycle at approved UPERC tariff benchmarks.
  • Greater Noida’s industrial belts — Ecotech, Kasna and Surajpur — frequently run projects at 250 kW to 1 MW, which makes open-access or behind-the-meter routes relevant once net-metered limits are reached.
  • Our commercial solar in Greater Noida page covers the utility-scale and mega-facility case.

The Approval Journey, In Order

Every utility follows the same logical sequence even when the paperwork differs:

1

Site survey and structural audit — roof type, load capacity, shading, distance to the panel room.

2

System design and SLD — string layout, cable routing, single-line drawings, protection coordination.

3

Net metering application — portal filing or division submission, processing fee, technical feasibility approval.

4

Statutory clearances — CEIG drawing approval and inspection where applicable.

5

Equipment procurement and installation — modules, inverters, structure, cabling, earthing, SPDs.

6

Meter commissioning — bi-directional or four-quadrant TOD meter installed and tested; flash and insulation-resistance tests completed.

7

Synchronisation and energisation — grid sync certificate, performance test, SCADA/monitoring handover.

The single biggest cause of delay is incomplete documentation, not engineering. A mismatch between the name on the electricity bill and the entity applying for the meter, a missing lease or ownership document, or an unsigned single-line drawing can add weeks.

What Happens Above 500 kW

The 500 kW regulatory cap in Haryana, and policy-based limits elsewhere, are where net metering stops being the natural fit. Above those limits, businesses typically evaluate:

  • Gross metering, where exported units are settled as a separate transaction rather than netted against consumption.
  • Open access / group captive, where a larger plant injects into the grid and the consumption is supplied under a separate arrangement — common for utility-scale plants in the Greater Noida and Noida industrial belts.
  • Behind-the-meter expansion, splitting capacity between a net-metered rooftop portion and a larger behind-the-meter or captive configuration.

Large sheds in these belts follow the warehouse playbook — see our solar for warehouses and logistics parks in NCR guide for sizing and metal-roof engineering.

Documents To Keep Ready Before You Apply

Most net metering delays are administrative, not technical. Keeping this set assembled before the application goes in will compress the timeline:

DocumentWhy it is needed
Latest electricity bills (ideally 3–12 months)Establishes sanctioned load, contract demand, tariff slab and account holder
Proof of building ownership or lease agreementNet metering is registered against the account holder's premises
Approved building drawing / property tax recordSite identification for the utility's survey and inspection
Single-line diagram (SLD) of the proposed systemTechnical submission accompanying the grid-connection application
GST registration and company detailsStandard for commercial and industrial connections
Authorised signatory ID proofSignatures on the application and the net metering agreement
Structural and roof details, with load auditTechnical feasibility review by the utility/inspectorate
CEIG drawings for plants above 100 kW or on HTStatutory approval before commissioning

The most common rejection cause is a mismatch between the name on the electricity bill, the entity applying for the meter, and the signatory on the agreement. Align all three before filing.

Practical Gotchas Worth Knowing Before You Design

Sanctioned load is the ceiling

If your sanctioned load is small but your roof is enormous, array size is limited — verify sanctioned load and contract demand before finalising layout.

Name on the bill matters

Net metering is registered against the electricity account holder. Tenants need the owner's consent and a documented arrangement.

Feeder capacity can bind before policy does

Distribution transformer capacity is verified by the utility; an export limit can be imposed even where policy allows the capacity.

Approval sequencing matters

Installing before the meter sanction can mean the system sits energised but unbilled, or needs re-testing.

Seasonal and site constraints

Monsoon inspections and rooftop access windows affect scheduling; plan the timeline accordingly.

Frequently Asked Questions (FAQs)

Is net metering available for commercial solar in Delhi?

Yes. Commercial rooftop solar under Delhi's licensed DISCOMs — BSES Rajdhani, BSES Yamuna and Tata Power-DDL — operates under the DERC green energy framework, with export recorded through a bi-directional meter and credited against consumption. Current capacity caps and credit terms should be confirmed with your division at the feasibility stage.

What is the maximum capacity for commercial net metering under DHBVN?

Commercial and industrial consumers under Haryana's regulations can install grid-connected rooftop solar up to 100% of their sanctioned load or contract demand, with a regulatory cap of 500 kW for net-metered installations.

How is exported solar credited on my bill?

Export is recorded through a bi-directional meter (four-quadrant TOD meters in Haryana) and credited in kilowatt-hours against your consumption. Credits roll forward across billing cycles — in Haryana through the financial year, under UP policy until the annual settlement.

Do I need CEIG approval for commercial solar?

For plants above 100 kW and for HT-connected systems at 11 kV or 33 kV, electrical drawing approval and inspection from the Chief Electrical Inspector to the Government (CEIG) are required alongside the utility's net metering sanction. Your EPC typically handles this liaison.

Can I install more solar than my sanctioned load?

Generally no — systems are installed up to 100% of sanctioned connected load. Beyond that, the economics shift to gross metering or open-access arrangements rather than rooftop net metering.

How long does commercial net metering approval take?

Typically a few weeks for the utility process plus a few days to weeks for CEIG clearances where applicable. A well-managed commercial project in NCR moves from site survey to grid commissioning in about 8–12 weeks.

Does net metering change the payback period?

It changes the project fundamentally. Net metering is what allows an array larger than your daytime load to still earn — surplus becomes bill credit instead of wasted generation. Without it, oversized commercial systems lose their economic case.

We are tenants — can we still get net metering?

Yes, provided the electricity account holder (usually the owner) consents and the arrangement is documented. Many tenants use a RESCO/OPEX structure, where the investor owns the plant and the host pays for the power.

Sources & Official References

Tariffs, capacity caps and approval processes are subject to change and to DISCOM approval. Verify against the official portals above before relying on any figure.

Related Commercial Solar Guides

Approvals Handled End To End

Get Your Net Metering Position Confirmed

The fastest path to a firm number is a documented feasibility check: sanctioned load, feeder capacity, applicable cap, meter route, and approval timeline for your specific site. We manage portal filing, technical feasibility, CEIG drawings, meter commissioning and synchronisation.

or email us at wecare@brightleaf.energy

Get In Touch

Schedule Your Free Rooftop Solar Consultation

Speak directly with our clean energy engineers. We will analyze your roof feasibility, calculate your government subsidy, and provide a customized quote.

Headquarters & Support

Visit our office or reach out to our team via phone or email.

Head Office Address

Spacetime Centre, DESEIN HOUSE, Greater Kailash II, Chittaranjan Park, New Delhi, Delhi 110048, India

Phone Helpline

+91 8800966764

Working Hours

Mon - Sat: 9:00 AM - 6:00 PM

Sunday: Closed

Subsidy filing & site inspection included free of charge
2hr
Response Time
Free
Site Visit
100%
Subsidy Help

Request a Free Solar Quote

Fill out your details and our solar expert will get in touch within 2 hours.

Continue Exploring Solar

Related Solar Guides & Cost Breakdowns

Keep reading the guides that answer the next question about cost, subsidy and payback.